Gooseberry Road pavement improvement project scheduled to begin this week

Date: 05/15/2013 

09:43

May 14, 2013

FOR IMMEDIATE RELEASE

Gooseberry Road pavement improvement project scheduled to begin this week

A pavement improvement project is scheduled to begin this week on Wyoming 431, also known as Gooseberry Road, between Worland and the Hot Springs County line.

McGarvin-Moberly Construction Co., of Worland is the prime contractor on the $5.06 million project.

The 19-mile project begins at reference marker 5 (near U.S. 20/Wyoming 789) and continues west to milepost 24 near Wyoming 120.

“The contractor will likely finish most work on the Gooseberry project in June. All work is dependent on favorable weather,” said Dan McAfee, Wyoming Department of Transportation resident engineer in Worland.

McAfee said motorists should expect delays of up to 20 minutes while the project is under way.

A description of the project includes milling asphalt, asphalt pavement paving, chip sealing and other work on 19 miles of Wyoming 431 between Worland and the Hot Springs County line.

McGarvin-Moberly was awarded the contract last July by the Wyoming Transportation Commission.

Contract completion date is Sept. 30, 2013.

WYDOT contact for this project is Resident Engineer Dan McAfee.
 