Sand Creek bridge epoxy overlay scheduled June 25 on WYO 32 project

June 20, 2018

Traffic delays of up to 15 minutes are expected Monday, June 25, during bridge work on the $1.96 million WYO 32 project between Lovell and Emblem.

"Paving is complete on the project, and the chip seal should happen later this summer," according to Wyoming Department of Transportation resident engineer Michael Miller of Basin.

The WYO 32 project is between mileposts 100 (Foster Gulch) and 112.72 (WYO 32's intersection with WYO 295).

"When complete, this rural highway will see new fence, bridge rehabilitation on the Foster Gulch, Sand Creek and Coon Creek bridges and an asphalt pavement mill, overlay and chip seal," said Miller.

Prime contractor is Mountain Construction Company of Lovell. Contract completion date is Oct. 31, 2018.