Wyoming Department of Transportation
roadway

Slope stabilization project progressing in Wind River Canyon

Date: 05/23/2013 

11:32

Thursday, May 23, 2013
 
FOR IMMEDIATE RELEASE 
 
Slope stabilization project progressing in Wind River Canyon
 
Construction of an 1,100-foot retaining wall is nearly complete on the $1.88 million slope stabilization project in Wind River Canyon between Shoshoni and Thermopolis on U.S. 20/Wyoming 789.
 
"The 1,100-foot wall is the longest of the five retaining walls on the project," said Robert Scheidemantel, Wyoming Department of Transportation resident engineer in Riverton.
 
Scheidemantel said the contractor's work crews are now working on a smaller retaining wall about four miles south of Thermopolis near Wedding of the Waters at the north end of Wind River Canyon. Construction of the other three "smaller" retaining walls will begin after this retaining wall is constructed.
 
Scheidemantel said the contractor's work schedule shows most work on the slope stabilization/retaining wall project expected to be complete in June. Project work will be shut down over the Memorial Day holiday weekend.
 
"Some paving is tentatively scheduled for late this month," Scheidemantel said. "The progress of work will be continue to be dependent upon favorable weather."
 
Expected work on the project includes grading, draining, placing crushed gravel and asphalt paving, and other highway improvements in Wind River Canyon.
 
Prime contractor for the project is Oftedal Construction, Inc., of Miles City, Mont. Contract completion date is Oct. 31, 2013.
 
WYDOT contact for this project is Resident Engineer Robert Scheidemantel.
 
For information about this news release, please contact Cody Beers, WYDOT public relations specialist.
Back to news list
Back to Top