US 14 resurfacing completed east of Greybull.

September 3, 2014

Nearly eight miles of US 14 east of Greybull got a new layer of pavement under a $2.8 million contract awarded to Lovell's Mountain Construction. The work was completed on Sept. 5, 2014, ahead of the Sept. 30, 2014 completion date included in the contract.