Wyoming Department of Transportation
construction

Project contracts

Lovell Main Street repairs to be funded with additional fuel tax revenue

Lovell Main Street repairs to be funded with additional fuel tax revenue

Date: 04/01/2014 

Cheyenne’s Reiman Corp. won a $4.9 million to replace and repair damaged concrete slabs on a mile of US 14A-WYO789 (Main Street) in Lovell. The road repairs account for $2.4 million of the total contract and will be paid for with revenue from the 10-cent fuel tax increase. Also included in the contract is replacing water and sewer lines under the road at a cost of $2.5 million. That will be paid for by the town of Lovell. The contract completion date is Oct. 31.

10-cent fuel tax revenue funding bridge rehabilitation

10-cent fuel tax revenue funding bridge rehabilitation

Date: 04/22/2014 

Thirteen bridges on highways in Big Horn, Fremont, Hot Springs, Park and Washakie counties will be rehabilitated under a contract won by Gerber Construction of Lehi, Utah, with the low bid of $2.9 million. The project will be funded with revenue from the 10-cent fuel tax increase and the completion date is Sept. 30, 2015.

WYO 433 to get pavement overlay and widening

WYO 433 to get pavement overlay and widening

Date: 09/17/2014 

Three-and-a-half miles of WYO 433 north of Worland will get a new layer of pavement and widened shoulders under a $5.7 million contract awarded to Oftedal Construction of Casper on Sept. 18, 2014. The contract completion date is Oct. 31, 2015.

WYO 130-230 section to get pavement overlay

WYO 130-230 section to get pavement overlay

Date: 12/17/2014 

A 12-mile section of WYO 130-230 north of Saratoga will get deteriorating pavement milled off and replaced with a new layer of pavement under a $3.7 million contract won by Mountain Construction Co. of Lovell. The contract completion date is Oct 31, 2015.

WYO 130 section to get pavement overlay

WYO 130 section to get pavement overlay

Date: 12/17/2014 

Worland’s McGarvin-Moberly Construction was the low bidder at $3.7 million for a new 2-inch layer of asphalt on 14 miles of WYO 130 between Centennial and Ryan Park. Parking areas along the highway also will be repaved, and the work is scheduled for completion by Aug. 31, 2015.

US 30 pavement overlay and shoulder widening to be paid for with increased fuel tax revenue

US 30 pavement overlay and shoulder widening to be paid for with increased fuel tax revenue

Date: 01/16/2015 

Simon Contractors and Subsidiaries of Cheyenne  won a $5.9 million contract for shoulder widening and a new layer of pavement on 6.6 miles of US 30 in Rock River and to the north. The shoulders will be widened to 6 feet from the current 1-2 feet to improve safety, and culverts will be replaced to improve drainage. The project will be paid for with revenue from the 10-cent fuel tax increase. With a final chip seal to follow next year, the contract completion date is July 31, 2016.

WYO 432 to get pavement overlay and chip seal

WYO 432 to get pavement overlay and chip seal

Date: 01/16/2015 

McGarvin-Moberly Construction of Worland was awarded a $3.1 million contract for resurfacing and chip sealing 10 miles of WYO 432 south of Worland. The work will be paid for with revenue from the fuel tax increase, and the contract completion date is Oct. 31, 2015.

US 85 north of Cheyenne to get new pavement

US 85 north of Cheyenne to get new pavement

Date: 11/14/2014 

Simon Contractors and Subsidiaries of Cheyenne was awarded a $3.86 million contract to grind off deteriorating pavement and replace it with a new layer of pavement on 10 miles of US 85 immediately east of I-25 north of Cheyenne. The work also will include a chip seal and will be paid for with revenue from the 10-cent fuel tax increase. The contract completion date is Oct. 31, 2015.

WYO 296 scheduled for pavement rehabilitation project

WYO 296 scheduled for pavement rehabilitation project

Date: 01/16/2015 

H-K Contractors of Idaho Falls submitted the low bid of $2.7 million for pavement rehabilitation on 6.5 miles of WYO 296 (Chief Joseph Highway). The work will include some shoulder flattening, a pavement overlay and a chip seal to the top of Dead Indian Pass about 37 miles northwest of Cody. The project will be paid for with revenue from the 10-cent fuel tax increase, and it is scheduled to be done by Sept. 30, 2015.

US 287 southeast of Lander to get pavement overlay

US 287 southeast of Lander to get pavement overlay

Date: 02/23/2015 

LeGrand Johnson Construction of Logan, Utah, was the low bidder at $4.9 million for improvements to nearly 5 miles of US 287 about 15 miles southeast of Lander. The work will include a new layer of pavement over the entire section and areas of full reconstruction at the south end of the project, where bentonite under the road is causing frost heaves that damage the pavement. Trenches lined with waterproof fabric will be used under the reconstructed road sections to prevent future heaves. The project will be funded with revenue from the 10-cent fuel tax increase, and it is scheduled to be done by...

Chip seals planned for northeast Wyoming highway sections

Chip seals planned for northeast Wyoming highway sections

Date: 02/23/2015 

Bituminous Paving Inc. of Ortonville, Minn., submitted the low bid of $3.4 million for chip sealing to extend the life of the pavement on highway sections in Campbell, Crook, Johnson, Sheridan and Weston counties by Aug. 31. About $1.9 million of the funding for the project will come from the 10-cent fuel tax increase.

Pavement overlay portion of US 26 project to be paid for with 10-cent fuel tax revenue

Pavement overlay portion of US 26 project to be paid for with 10-cent fuel tax revenue

Date: 03/23/2015 

Cheyenne’s Simon Contractors and Subsidiaries won a $3.2 million contract for improvements to nearly 4 miles of US 26 (Valley Road) in Torrington. The work will include isolated concrete slab replacement, milling off deteriorating pavement and replacing it with a new layer of asphalt. Lighting upgrades also are planned and sidewalks and curbs will be upgraded to meet Americans with Disabilities Act standards. The pavement overlay portion of the project between Main Street and County Road 53G will be funded with $783,000 in revenue from the 10-cent fuel tax increase. The contract completion date...

WYO 28 pavement overlay to be paid for with fuel tax increase money

WYO 28 pavement overlay to be paid for with fuel tax increase money

Date: 03/23/2015 

Worland’s McGarvin-Moberly Construction won a $1.97 million contract to grind off deteriorating pavement and replace it with a new layer of asphalt on nearly 4 miles of WYO 28 in the Red Canyon area about 11 miles south of Lander. The project will be paid for with revenue from the 10-cent fuel tax increase, and the contract completion date is Oct. 31, 2016.

US 20-26-87 pavement overlay scheduled in Douglas

US 20-26-87 pavement overlay scheduled in Douglas

Date: 04/29/2015 

Concrete Foundations Inc. of Douglas was the low bidder at $3.3 million for a contract to mill off deteriorating pavement and replace it with new pavement on US 20-26-87 (Richards Street) between Fourth Street and Mesa Drive in Douglas. The work will be paid for with revenue from the 10-cent fuel tax increase. A final layer of pavement will follow next year, with a contract completion date of June 30, 2016.

US 14-16-20 pavement overlay planned west of Cody

US 14-16-20 pavement overlay planned west of Cody

Date: 06/01/2015 

Pavement and bridge rehabilitation work will be completed on 4.5 miles of US 14-16-20 about 14 miles west of Cody under a $3.4 million contract won by low bidder Riverside Contracting of Missoula, Mont. The work will include rehabilitation of the Shoshone River and Trout Creek bridges at each end of the project, and a new layer of asphalt between the bridges. It will be paid for with revenue from the 10-cent fuel tax increase, and the contract completion date is Sept. 30, 2016.

Back to Top